Crew 286 Sol 07 Summary Report 19-NOV-2023
Sol: 07
Summary Title: “Rainy Mid-Mission Report Day.”
Author’s name: Roger Gilbertson
Mission Status: Nominal
Sol Activity Summary: Rain fell on and off throughout the night, causing the cancellation of both morning and afternoon planned EVAs. We performed interior tasks, monitoring bacterial growth, GreenHab work, and preparing and collating our Mid-Mission reports.
Look Ahead Plan: The science program will continue to monitor bacterial growth. Plaster mold preparation continues for test metal casting, as well as processing of LIDAR scans, photography and videography.
We will continue to monitor weather and surface conditions in hopes of revising our EVA proposals. Our visiting New York Times photojournalists plan to depart tomorrow morning, Sol 8.
Anomalies in work: none
Weather: rainy
Crew Physical Status: nominal
EVA: none
Reports to be filed: Sol Summary, Journalist report, Photos, Operations report, Green Hab report, EVA 7 request, Mid-mission report.
Support Requested: none