Operations Report – November 22nd

Crew 182+ Operations Report  22NOV2017

SOL: n/a

Name of person filing report: Shannon Rupert

Non-nominal systems: Lower deck wall heater is now operational, but
forced air furnace continues to alternate between warm and cool air.

I keep forgetting to report than the porthole came out of the main
airlock again.

Notes on non-nominal systems: nothing to report

Generator (hours run): Ran until 9 am, then off until 5:45 pm

Solar— SOC 97 % when generator was turned on

Diesel –  not checked %

Propane –  not checked psi.

Ethanol Free Gasoline (5 Gallon containers for ATV) –   0 gallons.

Water (trailer) –  0 gallons.

Water (static) –  350 gallons

Trailer to Static Pump used –  no

Water (loft) – Static to Loft Pump used –  not known

Water Meter:  not checked

Toilet tank emptied: Yesterday

ATV’s Used: (Honda, 300, 350.1, 350.2, 350.3) 350 s moved to their normal place

Oil Added? no

ATV Fuel Used:  not known Gals

# Hours the ATVs were Used today: 5 min

Notes on ATVs: The 300’s battery is low, did not jump today.

Deimos rover used:  yes

Hours:

Beginning charge:

Ending charge:

Currently charging: yes

Sojourner rover used:  ASSIGNED TO DIRECTOR, not yet ready

Hours:

Beginning charge:

Ending charge:

Currently charging: yes

Spirit rover used:  Not yet ready

Hours:

Beginning charge:

Ending charge:

Currently charging: no

Opportunity rover used:  not yet ready

Hours:

Beginning charge:

Ending charge:

Currently charging: no

Curiosity rover used:  no yet ready

Hours:

Beginning charge:

Ending charge:

Currently charging: no

HabCar used? Yes, hauled 100 gallons of water and emptied the 100
gallons Brandon got yesterday

General notes and comments: Cleaning day

Summary of internet: not known

Summary of suits:  I checked all of them today.  Two more chargers not
functional.  Unfortunately one of the helmets was cracked in such a
way that it will not be repairable.  Removed from service.  One of the
backpacks is missing one of the two straps that hold the collar on the
frame.

Summary of Hab operations: Brandon and I cleaned the Hab.  It took all
morning and then some.  Looking good now.

Summary of GreenHab operations:  Watered.  Used 4 gallons.  Removed
hose from frost free faucet.  Crews should get water from faucet
without hose from now until spring to prevent freeze up.  I’ve been
thinking I may get the 55 gallon drum from town to keep water in
inside the GreenHab.  It might also increase humidity, which seems to
stay around 16 %.

Summary of ScienceDome operations: Nothing to report.

Summary of RAMM operations:  Nothing to report.

Summary of health and safety issues:  We are safe and we are healthy.

Questions, concerns and requests to Mission Support:  Nothing, thank you.