Crew 207 Sol Summary Report 26-Mar-2019
Sol: 10
Summary Title: A Day of Rest and Solitude
Author’s name: Julielynn Wong
Mission Status: Nominal
Sol Activity Summary:
Crew 207 continued 3D printing in the Hab today. We began printing on our third 3D printer today.
The following items were identified as useful to 3D print at MDRS:
Funnels (small and large)
COM has taken over GHO duties. XO has taken over ENG duties.
Look Ahead Plan: Continue 3D printing in Hab. Complete data collection for bike study. Prepare for arrival of Crew 208.
Anomalies in work: None
Weather: Status
Crew Physical Status: Nominal
EVA: n/a
Reports to be filed: Operations, Greenhab
Support Requested: None